ODOT Report: I-75 Mill Creek Expressway

 

Overall Project Update

The project environmental document was approved by the Federal Highway Administration in May 2009. Work on various phases is progressing. The first phase of work is scheduled to begin construction in the spring of 2010. This phase will construct the new Monmouth Street connection between Central Parkway and Colerain Avenue. ODOT has begun the Right-of-Way acquisition process on the first four phases in the corridor. Design of the Mitchell Ave. phase and Colerain/Beekman phases will be completed in August 2010. Hopple Street interchange phase design is approximately 50% complete. Phase 6 design is approximately 40% complete. Final design of phases 5 and 7 is scheduled to begin in spring 2010. At this time, construction and design funding for phase 8 has not been identified.
Phase 2, the Monmouth overpass phase, is being funded through the American Recovery and Reinvestment Act.   

Corridor Project Phasing and Schedule

Due to cost, constructability, and time constraints, the Mill Creek Expressway project has been split into eight phases of construction. The following table provides a brief description of each phase and tentative major milestone dates:

Phase

Project Description

Construction Cost (million)

Right-of-Way Acquisition Start

Construction Start

Construction End

1

Mitchell Ave. Interchange

$57.7

Started

March 2011

August 2014

2

Monmouth St. Overpass

$7.1

Started

April 2010

October 2011

3

Colerain/Beekman/I-74 Interchange

$8.8

Started

May 2011

September 2012

4

I-75 from Western Hills Viaduct to Monmouth Overpass (includes Hopple Interchange)

$99.6

Started

March 2013

August 2016

5

I-75 from Monmouth Overpass to Mitchell Ave. (includes I-74 Interchange and I-74 improvements)

$150.2

October 2011

March 2015

August 2018

6

RR Overpass South of Norwood Lateral

$21.4

August 2010

March 2014

September 2015

7

I-75 Mainline from Mitchell Ave. to the Norwood Lateral

$39.1

July 2011

March 2016

May 2018

8

I-75 Mainline from the Norwood Lateral to Cross County Highway

$148.1

August 2014

March 2018

May 2020

Revive Cincinnati Effort:

ODOT is participating and assisting this City-led effort by providing information on our projects in the Hamilton I-75 corridor. As results and recommendations are adopted by the City, ODOT will work with the various partners to incorporate them when feasible.

For More on the Project visit here: I-75 Mill Creek Expressway

Published in: on April 16, 2010 at 17:53  Leave a Comment  

ODOT report (District 8 Southwest Ohio)

We are adding some more topics to discuss in our weekly blog:

  • Road construction and major passage projects.
  • Future local government plans and projects that could be an impact to your community. 

4/15/2010 

Lane Closures Scheduled for I-75/Monmouth Street Overpass Work

HAMILTON COUNTY (Thursday, April 15, 2010) – Lane closures for next week to accommodate work to reconstruct

the Monmouth Street overpass at Interstate 75 are as follows:

Monday, April 19: Right two lanes northbound I-75, closed from 10 p.m. to 5 a.m.

Ramp from Bates Avenue to westbound I-74, closed from 10 p.m. to 5 a.m.

Tuesday, April 20:  Left two lanes of north and southbound I-75 from 10 p.m. to 5 a.m.

Wednesday, April 21: Right two lanes of southbound I-75 from 10 p.m. to 5 a.m.

This work at the I-75/Monmouth Street overpass is the start of the $664 million Interstate 75 Mill Creek Expressway Project, which will improve traffic flow and enhance safety of the I-75 corridor from the Western Hills Viaduct to north of the Paddock Road interchange in Hamilton County. Over the course of 10 years, construction will rehabilitate eight miles of existing lanes and construct an additional lane in each direction.

The Monmouth Street work will remove and reconstruct the overpass, and reconstruct and convert Monmouth to a local through street between Central Parkway and Colerain Avenue. In addition, the Bates Avenue Bridge and the pedestrian bridge between Colerain Avenue and Central Parkway will be removed to clear overhead obstruction to future construction on I-75. Work on the new overpass is to be completed by Sept. 30, 2010, with completion of the entire phase scheduled for Aug. 31, 2011. The Great Lakes Construction Company was awarded the $7.192 million contract.

I-75 Lane Closures Scheduled for Monmouth Work

Published in: on April 16, 2010 at 17:47  Leave a Comment  

Employment Situation Summary (US)

 

Ohio State Report is scheduled to be released later today 4-16 and the county map breakdown released 4-20. We will update both reports upon release.

THE EMPLOYMENT SITUATION — MARCH 2010

Nonfarm payroll employment increased by 162,000 in March, and the unemployment
rate held at 9.7 percent, the U.S. Bureau of Labor Statistics reported today.
Temporary help services and health care continued to add jobs over the month.
Employment in federal government also rose, reflecting the hiring of temporary
workers for Census 2010. Employment continued to decline in financial activi-
ties and in information.

Household Survey Data

In March, the number of unemployed persons was little changed at 15.0 million,
and the unemployment rate remained at 9.7 percent. (See table A-1.)

Among the major worker groups, the unemployment rates for adult men (10.0 per-
cent), adult women (8.0 percent), teenagers (26.1 percent), whites (8.8 per-
cent), blacks (16.5 percent), and Hispanics (12.6 percent) showed little or no
change in March. The jobless rate for Asians was 7.5 percent, not seasonally
adjusted. (See tables A-1, A-2, and A-3.)

The number of long-term unemployed (those jobless for 27 weeks and over) in-
creased by 414,000 over the month to 6.5 million. In March, 44.1 percent of
unemployed persons were jobless for 27 weeks or more. (See table A-12.)

The civilian labor force participation rate (64.9 percent) and the employment-
population ratio (58.6 percent) continued to edge up in March. (See table A-1.)

The number of persons working part time for economic reasons (sometimes re-
ferred to as involuntary part-time workers) increased to 9.1 million in March.
These individuals were working part time because their hours had been cut back
or because they were unable to find a full-time job. (See table A-8.)

About 2.3 million persons were marginally attached to the labor force in March,
compared with 2.1 million a year earlier. (The data are not seasonally adjusted.)
These individuals were not in the labor force, wanted and were available for
work, and had looked for a job sometime in the prior 12 months. They were not
counted as unemployed because they had not searched for work in the 4 weeks pre-
ceding the survey. (See table A-16.)

Among the marginally attached, there were 1.0 million discouraged workers in
March, up by 309,000 from a year earlier. (The data are not seasonally adjusted.)
Discouraged workers are persons not currently looking for work because they be-
lieve no jobs are available for them. The remaining 1.3 million persons margin-
ally attached to the labor force had not searched for work in the 4 weeks pre-
ceding the survey for reasons such as school attendance or family responsibili-
ties. (See table A-16.)

Establishment Survey Data

In March, nonfarm payroll employment rose by 162,000. Job growth continued in tem-
porary help services and in health care. Federal government employment increased
due to the hiring of temporary workers for Census 2010. Job losses continued in
financial activities and in information. (See table B-1.)

Temporary help services added 40,000 jobs in March. Since September 2009, tempor-
ary help services employment has risen by 313,000.

Employment in health care continued to increase in March (27,000), with the larg-
est gains occurring in ambulatory health care services (16,000) and in nursing and
residential care facilities (9,000).

In March, employment in mining increased by 8,000. Monthly job gains in mining
have averaged 6,000 over the past 5 months.

Employment in federal government was up over the month, reflecting the hiring of
48,000 temporary workers for the decennial census.

Manufacturing employment continued to trend up in March (17,000); the industry has
added 45,000 jobs in the first 3 months of 2010. Over the month, job gains were
concentrated in fabricated metal products (9,000) and in machinery (6,000).

Employment in construction held steady (15,000) in March. The industry had lost an
average of 72,000 jobs per month in the prior 12 months.

Over the month, employment changed little in transportation and warehousing,
leisure and hospitality, retail trade, and wholesale trade.

In March, financial activities shed 21,000 jobs, with the largest losses occur-
ring in insurance carriers and related activities (-9,000). Employment in the
information industry decreased by 12,000.

The average workweek for all employees on private nonfarm payrolls was up by
0.1 hour to 34.0 hours in March. The manufacturing workweek for all employees
increased by 0.2 hour to 39.9 hours, and factory overtime was up by 0.1 hour
over the month. In March, the average workweek for production and nonsuper-
visory employees on private nonfarm payrolls increased by 0.2 hour to 33.3
hours. (See tables B-2 and B-7.)

In March, average hourly earnings of all employees on private nonfarm payrolls
fell by 2 cents, or 0.1 percent, to $22.47, following a 4-cent gain in February.
Over the past 12 months, average hourly earnings have risen by 1.8 percent. In
March, average hourly earnings of private production and nonsupervisory employ-
ees fell by 2 cents, or 0.1 percent, to $18.90. (See tables B-3 and B-8.)

The change in total nonfarm payroll employment for January was revised from
-26,000 to +14,000, and the change for February was revised from -36,000 to
-14,000.

____________
The Employment Situation for April is scheduled to be released on Friday,
May 7, 2010, at 8:30 a.m. (EDT).

 

For more data visit here: Employment Situation Summary

Cincinnati Homes for Sale (Daily Activity Report)

New Listings 237  
Back on Market 12  
Price Increases 6  
Price Reductions 230  
Pendings 126  
Solds 66  
Expireds 4  
Inactives 46  
Follow

Get every new post delivered to your Inbox.

Join 320 other followers